From Railway Age 11-22-24 Vol. 77,
No 21. 931-934
Abstract of a paper present before the Western Society of Engineers Chicago, on
November 17.
Missouri River
Bridge at Blair, Neb., Rebuilt
Old Structure in Excellent Condition After Forty Years'
Service-Too Light for Modern Loads
By O. F. Dalstrorn
Bridge Engineer, Chicago & North Western. Chicago
In 1923 THE CHICAGO & NORTH WESTERN reconstructed its bridge over the Missouri river near Blair, Neb. This bridge was built in 1882-83. The superstructure, designed for the small engines and light cars of that day, was not strong enough for present day loads. The substructure, however, was of adequate strength. The four river piers were used in the reconstructed bridge without any remodeling to carry the new spans, while the piers and abutments of the approaches were remodeled to receive the new approach spans, which differed in type and detail from the old spans. The old bridge provided originally for three 330-ft. through truss spans over the river channel, with approaches consisting of one 110-ft. deck truss span and one 22-ft. 6-in. deck plate girder span at each shore. The 110-ft. truss span in the west approach was replaced with a 176-ft. truss span after the bridge was completed. The total width of waterway provided for in the design was about 1,000 ft. The clear head room was 50 ft. above mean high water. The width of waterway necessary was determined by the width of the river at points some miles down stream from the proposed site, where the river, confined by banks on both sides, was somewhat less than 1,000 ft. wide, the waterway being clearly sufficient for the river at flood stage. The clear head room under the bridge was established by government engineers to provide adequate clearance for existing and for contemplated river traffic.
The
Substructure Was in Good Condition
The substructure for the three 330-ft. river spans consists of four masonry
piers on caissons sunk to rock. The piers under the shore ends of the 110-f t.
approach spans were concrete-filled steel cylinders on pile foundations. The
22-ft. 6-in. girder spans at the extreme ends of the bridge extended shoreward
from the cylinder piers, their shore ends resting on masonry abutments buried in
the embankment. The purpose of the short girder spans was to fix the end of each
embankment far enough back from the cylinder pier to bring the slope below the
tops of the cylinders.
The stone for the piers was quarried at Mankato, Minn., and is an excellent
grade of limestone, originally of a yellow color. The cutwaters of the upstream
ends of Piers 4 and 5 were of blue granite, quarried at St. Cloud, Minn. The
face stones were laid in Portland cement mortar. The backing was laid in
Milwaukee cement mortar, except that laid during freezing weather when Portland
cement was used throughout. The specifications for the masonry were very
exacting as to quality of materials and workmanship.
When the reconstruction of the bridge was proposed, an inspection of the piers
was made to determine whether their condition and probable length of life would
justify erecting the proposed new superstructure on them. Every face stone in
the four piers, above water level, was inspected. This inspection showed two
kinds of weathering effects; some stones were pitted all over 1/4-in. to 3/4-in.
deep and were rough to the touch, as if some soluble ingredient had been
dissolved out. The other stones were wholly free from pitting, but many of them
were spalling slightly. Fresh surfaces where spalls had dropped away recently
and a few spalls still clinging to the stones, showed that the spalling was
still going on. The loss by spalling or pitting, however, was so small that it
was hardly appreciable except in one stone on the west side of Pier 3, near low
water level, which had spilled off to a depth of nearly six inches over its
entire face. This stone has since been faced with concrete.
The mortar in the joints was in excellent condition, no evidence of
deterioration being found. The piers have never been pointed since they were
built. Small dabs of mortar spilled on the lower courses during construction had
hardened on the stones and could be dislodged only by a sharp blow with a
hammer.
A number of cracked stones were found on this inspection. There were also a few
cracks at joints. All except two cracks in the stones were vertical, generally
near the middle of the stone and extended through only one stone. Two of the
cracks were horizontal, one of them in a stone that showed signs of lamination.
The largest cracks would barely admit the point of a knife blade, while the
smallest were hardly more than visible. All of them appeared to be old cracks.
The vertical cracks were probably caused by uneven bedding of the stones when
laid, the stones cracking in vertical planes under the action of the
superimposed load. The cracking permitted the stones to adjust themselves to the
uneven bedding and no further developments followed. On the east side of Pier 6,
near the north end, is a joint crack running through five courses and through
the connecting segments of the horizontal joints. There was no evidence of
displacement of the stones, the crack being only about 1/16-in. wide. From the
records of the inspection it was estimated that the piers were still good for
not less than 50 years and probably much longer.
The piers under the shore ends of the 110-ft. approach spans consisted
originally of two concrete-filled cylinders in each pier, built on pile
foundations. The cylinders were 5 ft. in diameter, 12 ft. apart center to
center, and connected by steel bracing from top to bottom. The shells were of
5/16 in. metal. The cylinders for the west pier were 42 ft. 9 in. long; for the
east pier they were 13 ft. longer than those of the west pier, on account of the
lower level of the ground line at the east pier.
In 1900 it became necessary to remodel the two-cylinder pier in the east
approach, making it a four-cylinder pier with bolsters on top, on account of a
slow westward movement of the east embankment. No change in the superstructure
was necessary. When the bridge was reconstructed in 1923, the pier was remodeled
by cutting down the cylinders and lowering the bolsters.
On account of disturbances in the west embankment in 1884, it was decided that
the end of that embankment should be kept farther away from Pier 6. Accordingly
the 110-ft. span was taken out in 1885 and replaced with a new span 176 ft.
long, the shore end resting on a concrete and I-beam grillage, 12 ft. by 24 ft.
by 6 ft., buried in the embankment, which was sloped back to conform to the
outline of the new span. The 22-ft. 6-in. girder span was re-erected at the end
of the new span. The upper portion of the old cylinder pier was removed to a
level slightly below the surface of the new slope.
In the reconstruction of the west approach in 1923 the 176-ft. deck truss span
was replaced by two deck plate girder spans and a steel bent. The substructure
for the steel bent consisted of two separate concrete pedestals built on
concrete foundation piles about 40 ft. long. These pedestals were placed 23 ft.
6 in. apart to permit a pile driver to work from the track with leads suspended
outside the bridge, the vertical clearance below the span being too small for a
pile driver. This accounts for the width of the bent at its base, which is
considerably more than required for stability.
The old concrete and I-beam grillage at the end of the truss span and the old
abutment were remodeled at the bridge seats to fit the new girder spans. The new
approach spans were so designed as to require but little remodeling of the
substructure.
In the reconstruction of the east approach the old 110-ft. deck truss span was
replaced with a deck plate girder span of corresponding length. The old cylinder
pier was cut down, the I-beam grillages replaced at the lower level and a
transverse bolster built of I-beams set on the grillages to carry the girder
span. To carry the end of the deck truss span while the pier was being cut down
and remodeled, a special steel bent was built and set in place under the
bearings.
Approaches Were on Unstable Foundations
The approaches at both ends of the bridge originally consisted of timber
trestles on one per cent grades. The trestle at the west end was not
contemplated in the original plan, which provided that this embankment should be
finished to grade while the bridge was being built. When this embankment had
been brought up to grade to within about 300 ft. of the west end of the bridge
as established, a settlement of about 6 ft. occurred during the night of July
19, 1883. The ground at the sides of the embankment rose about 6 ft. at the same
time. Borings revealed a layer of soft mud below the top layer of hard material,
evidently marking the course of an old channel. The filling was continued until
the embankment was again brought to grade; settling continued during the
progress of filling, the ground at the sides rising about 14 ft. before
equilibrium was established. It was estimated that the total settlement of the
embankment was over 40 ft.
The embankment adjacent to the bridge was not carried up to grade at this time.
The east end was leveled off at the full width of the finished embankment about
35 ft. below the level of track on the bridge, and a trestle about 220 ft. long
was built to carry, traffic until the embankment could be finished. The
embankment was finished to grade up to the end of the bridge in 1884, but almost
immediately after completion a section adjacent to the bridge settled about 10
ft., carrying the cylinder pier down with it. The span carried by the cylinder
pier was held to grade during the settlement by blocking laid up as the
settlement progressed. This settlement was near enough to Pier 6 to produce a
slight movement, the top of the pier being displaced about 9 in. toward the
river. It was not believed that the pier had been cracked or otherwise damaged,
the displacement being accounted for o by compression in the timber cribwork in
the lower part of the pier. There has been no disturbance or unusual settlement
of the embankment since 1884, and no further displacement of Pier 6 since that
date. It was on account of these disturbances that the 110-ft. span was replaced
in 1885 by the 176-ft. span previously mentioned.
The history of the east approach is quite different from that of the west
approach. Since the material for filling had to come from the cut on the west
side of the river, this embankment could not be constructed until after the
bridge should be completed. Accordingly a timber trestle 3,000 ft. long was
built to carry traffic temporarily. Filling was begun in the winter of 1883-84
at the end farthest from the bridge. In March, 1884, the highwater carried away
1,600 ft. of the trestle adjacent to the bridge, being all of the trestle not
protected by the filling. The trestle was rebuilt at once. Filling was continued
during 1884, the portion not disturbed by the March high water being filled to
grade and the filling well started under the rebuilt portion that year. The
entire embankment was completed in 1885.
No settlement occurred during the filling of the east approach such as those
that disturbed the west approach. However, a very slow westward movement of the
cylinder piers following the completion of the embankment showed that the end of
the embankment was moving toward the river. There was also a slight vertical
settlement of the cylinders, as would be expected. The records do not show when
this movement was first noticed, but it probably began before the embankment was
actually completed. As the pier carried the fixed end of the deck truss span,
this span was carried westward with the cylinders and embankment. When the
movement had carried the deck span westward a few inches it became necessary to
shift the pedestals on the cylinders eastward, drawing the span back to its
original position to prevent it from crowding against the east river span. By
1900 the top of the cylinder pier had moved toward the river about 10 1/2 in.
and was still moving. The end bearing of the span had by this time been shifted
toward the east side of the pier as far as it could go. The west end of the span
was crowding against the end of the adjacent river span, making it necessary to
repeat the shifting of the deck span. To remedy this condition and provide for
future movement of the pier, a pair of cylinders, similar to those in the
original pier but only 35 ft. long, were set 8 ft. 5 in. back of the old
cylinders and filled with concrete. The old cylinders were cut down about 1 ft.
and two I-beam grillages filled with concrete were set on top of the old and the
new cylinders, parallel to the axis of the bridge, forming bolsters for carrying
the truss bearings.
When the cylinder pier had been remodeled the deck span was moved back to its
normal position. Also at this time the fixed and expansion bearings of the span
were interchanged, the expansion bearing being transferred to the cylinder pier
so that any further displacement of this pier would take place without
displacement of the span. The slow movement of the pier continued after the new
cylinders had been put in, all of the cylinders moving with the embankment. By
1920 they had moved so far that the base castings under the bearing rollers were
almost in contact with the diagonal truss members. This was corrected in 1921 by
sliding the base castings back a few inches and anchoring at a new place on the
bolsters.
In 1921 a quantity of heavy stone from the abutments of an old bridge near
Missouri Valley was put in along the foot of the slope where it projects into
the river, the outer layer being stones of boulder size. These large stones,
being massive enough to withstand the ice and the current at high-water, have
protected the embankment against scour and no further displacement of the pier
has been observed since this was done. The total displacement of the top of the
old cylinders from their original position is 21 in.
Superstructure Showed Little Deterioration
The entire superstructure was in excellent condition when taken down. No
reinforcing and very little repair work had been done on any of the spans during
their forty years of service. In 1900 the short sections of eye bars in the
adjustable counters in all three river spans were replaced with new pieces, on
account of defects that developed in the original bars. In 1920 the connection
angles in a number of stringers of the river spans were found to be cracked in
the fillets and were replaced with new angles-12 pairs in all. In the same year
several floor beams in the 110-ft. and 176-ft. approach spans were repaired
where they had developed cracks in the webs near the bottom of the stringer
connections, evidently due to the thrust from the ends of the bottom flanges of
the stringers. In 1923 some cracked connection angles of stringers in the deck
truss spans were on the order to be replaced, but the spans were taken out
before it was necessary to do the work. The cause of these failures in the floor
member details, at this late date, was probably the heavy cars which by 1920
were more severe on the floor members than the locomotives. There had been no
increase in the weight of locomotives over the bridge for about 20 years.
There was no evidence of deterioration of the structure when taken down. There
were no shoulders on the pins and no elongated pin holes. A number of the pins
stuck fast in the top chords and the posts. Those in the chord that could not be
loosened were burned off. Those in the posts were left there, the eye bars being
simply slipped over the ends of the pins.
The history of this bridge is a good demonstration of the endurance of such a
structure under favorable conditions of service and maintenance. It represented
the best class of material and workmanship of its day. Traffic was always
comparatively light, only a few trains a day each way. Situated at the summit of
long, heavy approach grades, it was never subjected to the high speed of trains,
which could scarcely attain the speed limit of 10 miles per hour allowed.
Loading was always well within the capacity of the bridge until recent years
when trains of heavy cars probably produced stresses in light truss members
above the limits allowed in good practice. Rigid inspection was maintained by
the general bridge inspector and the division inspectors. After forty years of
service, there were no indications from which to determine the limit of life of
the structure under existing conditions. It looked good for 40 or 50 years more
of the same kind of service, and gave no means of fixing the limit, since there
was no measurable deterioration.
The three river spans were taken down in shape for re-erection. One of these has
been assigned for re-erection over the Wind river near Riverton, Wyo., while the
other two spans are stored at Blair. The deck spans were taken down as scrap,
their size and shape making it impracticable to find a place to use them.
The New Superstructure
The new superstructure was designed for Cooper's Class E-60 loading. It was
designed and built under the American Railway Engineering Association
specifications for steel railway bridges, edition of 1923. The new spans were
fitted to the four old river piers without any remodeling of the piers. In order
to make the three river spans alike it was necessary to load Pier 6
eccentrically. The center line of truss bearings is 6 in. west of the center
line of pier, and the center line of girder bearings is 2 ft. 11 in west of the
center line of pier. This eccentricity of loading was due to the displacement of
Pier 6 toward the river as already indicated. As the pier was of ample strength
for the new loading, and as the eccentricity of loading was in the direction
opposite to the displacement of the pier, it was considered of too little
importance to justify a special length of span to fit this pier.
The old deck truss spans of the approaches were replaced with deck plate girder
spans and the substructure remodeled accordingly. The 176-ft. span of the west
approach was replaced by two short girder spans and a steel bent, a more
economical type than the single long span.
The new superstructure was designed by the American Bridge Company and
fabricated at its Gary plant. The contract for the erection of the new
superstructure was also awarded to the American Bridge Company. This contract,
which was distinct from the contract for design and fabrication, included the
construction and the removal of the falsework, the removal of the old
superstructure and the erection of the new. The railway company furnished all
the piles and lumber for the falsework, but none of the framing iron or the
steel I-beams for the falsework deck. The contractor was required to take down
the three river spans without damage to the members, so that these spans could
be re-erected elsewhere. The approach spans were to be taken down and loaded in
convenient way, except that stringers were not to be damaged, and were to be
loaded separately in cars. These stringers were of a size and length making them
good material to keep on hand for ordinary falsework.
A convenient storage yard was available on the west bank of the river just north
of the bridge.
The Erection Proceeded Rapidly
The falsework for the three river spans, designed by the American Bridge
Company, consisted of framed bents on piles. On the bents were set the I-beams,
24 in. by 115 lb. by 36 ft. which carried the traffic and the structures during
the removal of the old and the erection of the new bridge. The piles furnished
were Oregon fir, 70 ft. long, very large and straight. In approving the
falsework plan, the railway company changed the longitudinal and transverse
braces from nominal small sizes to 12-in. by 12-in. and 8-in. by 16-in., in
order to secure good bridge timber from the salvage. This extra-heavy bracing
rendered good service later when a sudden rise of the river threatened to
destroy the false-work in the west channel spans.
No falsework was provided for the erection of the approach spans. The 176-ft.
truss span in the west approach was shifted northward 19 ft. and landed on
temporary pile piers, and the new spans and bent erected with cranes working
from both levels. Traffic was suspended about ten hours while this change was
being made. The old truss span in the east approach was cut up in place with
Oxweld, outfits and loaded direct into cars. The new deck girder span was
erected by using two locomotive cranes, one at each end, to set the girders in
place. Traffic was suspended 6 1/2 hours for this operation.
There were only two periods of suspension of traffic in, the entire program of
erection. Some interruptions to train movement occurred when it was necessary to
hold trains until the locomotive cranes could let go of the work in hand to move
off the bridge and get in the clear.
The erection of steel in the west river span was begun October 13. From that
date erecting and riveting were practically continuous until the last member of
the east river span was erected on December 22. The 110 ft. and the 22 ft. 1 in.
girder spans of the east approach were erected on December 19. The riveting of
the truss members was completed on January 15, 1924. The erection of the
brackets for planking and handrailing followed the other work and was completed
on January 19.
The thoroughness with which the work of the contractors for fabrication and
erection was planned and executed is demonstrated by the beginning of delivery
of steel at the bridge site within five months after receiving the order; and by
the completion of the entire program of erection, including the construction of
the falsework and its removal, in a little more than six months.
Deck and Track
Ample provision is made for the protection of the deck and bridge against
damage by derailments. The steel guard angles and 4-in. by 8-in. guard planks
protect the ties against damage by ordinary derailments. The 10-in. by 12-in.
guard rails, notched over the ends of the ties and bolted to every tie, hold the
ties against bunching by derailed trucks, and prevent derailed cars from
drifting into the trusses.
The free movement of the rails and expansion ends of spans, independent of each
other, is provided for in five expansion joints in the rails, conforming in
position to the expansion ends of the spans. An expansion joint in the rails at
each end of the bridge protects it against damage from movement of the rails in
the track beyond the ends of the bridge. The deck, track and railing were placed
by railway company forces. The total weight of the spans aggregated 5,122,379
lb.